Quick answer: To estimate soffit and fascia, add the eave and rake lengths, multiply by the soffit width for the soffit area, and use the same total length for fascia, F-channel and J-channel. A house with 120 ft of eave, 60 ft of rake and 16 in soffits has 240 sq ft of soffit, or 264 sq ft with 10% waste, which is 22 vinyl panels, 198 ft of 1x6 fascia and 180 ft each of F-channel and J-channel.
Your measurements
cut pieceTotal lengthPiece length
A length built from stock pieces: total length divided by piece length, rounded up, with the last piece cut.
Results update as you type. The link in your address bar saves these entries.

Results

Soffit area to order
264 sq ft
240 sq ft of soffit (180 ft of run x 16 in) plus 10% waste
Soffit panels
22 panels
Vinyl 12 in x 12 ft panels, 12 sq ft each
Fascia
198 ft
1x6 boards: 17 pieces at 12 ft including waste
F-channel (wall side)
180 ft
Eave plus rake; 15 pieces at 12 ft. Nailed to the wall or a 2x2 nailer, with 1/4 in left at each joint for expansion
J-channel (fascia side)
180 ft
Eave plus rake; 15 pieces at 12 ft. Skip if the aluminum fascia cover has a built-in lip
Soffit vents
Size separately
Vented panel gives about 5 to 10 sq in of net free area per foot, printed on the carton. IRC R806.2 wants 1 sq ft per 150 sq ft of attic, or 1 per 300 when 40 to 50% of it is at the ridge; size the count with the attic ventilation calculator

Soffit and Fascia formula

Run = Eave length + Rake length
Soffit area = Run x Soffit width (in) / 12 x (1 + waste %)
Panels = Soffit area / panel coverage, rounded up  (vinyl 12, aluminum 16, plywood 32 sq ft)
Fascia = Run x (1 + waste %);  F-channel = J-channel = Run

Worked example

A ranch with 90 ft of eave, 40 ft of rake and 24 in soffits: run = 130 ft, area = 130 x 24 / 12 = 260 sq ft. With 10% waste that is 286 sq ft. Aluminum panels cover 16 sq ft each, so 286 / 16 = 17.9, or 18 panels.

Fascia: 130 x 1.1 = 143 ft, which is 143 / 12 = 11.9, so 12 pieces of 12 ft aluminum fascia cover. F-channel along the wall and J-channel at the fascia are 130 ft each, or 11 pieces of 12 ft apiece.

Quick reference

Soffit area and panels per 100 ft of run (10% waste)
Soffit widthAreaVinyl panels (12 sq ft)Aluminum panels (16 sq ft)
12 in100 sq ft107
16 in133 sq ft1310
18 in150 sq ft1411
24 in200 sq ft1914
30 in250 sq ft2318
36 in300 sq ft2821

Measuring eaves and rakes

Walk the house and measure every horizontal roof edge for the eave total, then measure the sloped gable edges for the rake total. Rake length is the sloped distance, not the horizontal width of the house; a 30 ft wide gable at 6/12 pitch has two rakes of about 16.8 ft each. A hip roof has no rakes, only eaves all the way around.

Measure the soffit width from the wall to the outside face of the fascia. Panels run perpendicular to the wall and are cut 1/4 inch short of the channel-to-channel measurement, so panel count is driven by area, not length; a soffit wider than 24 inches needs a nailer at mid-span. Plywood soffit is ripped from 4 x 8 sheets of 3/8 inch exterior grade.

Fascia, channels and ventilation

Wood fascia is 1x6 for 2x6 rafter tails and 1x8 for 2x8 tails, primed on all sides. Aluminum fascia cover wraps sound wood only; rotted sections get replaced first. It slides under the drip edge, hooks the bottom of the board, and takes color-matched trim nails every 16 inches; lap joints 1 inch and start at the far end so laps face away from the approach. Gutters come down first and go back on hidden hangers screwed through the cover. F-channel on the wall takes the inner edge; J-channel or the fascia cover's lip takes the outer edge.

Vented panels give about 5 to 10 sq in of net free area per foot, printed on the carton. A 1,500 sq ft attic on the 1/300 rule needs 360 sq in of intake. That is 36 ft of fully vented panel at 10 sq in per foot, so every third panel on a 120 ft eave. On the 1/150 rule with no ridge vent, vent the whole eave. Rake soffit is not intake. Every opening, including the gap where soffit meets rake, must be screened to 1/16 to 1/4 inch (IRC R806.1) against wasps, birds and squirrels.

What this calculator leaves out

The result is panels, fascia and channels. It leaves out trim nails (about 1 lb per 100 ft of run), sub-fascia, drip edge, baffles, louvered vents for plywood, and the gutters and hangers. Rotted rafter tails found after the old soffit comes down are the usual change order.

Mistakes that cost money

  • Every third panel vented meets 1/300 with a ridge vent; on the 1/150 rule with no ridge vent the whole eave needs vented panel.
  • Nailing vinyl or aluminum tight buckles it in summer; center the nails in the slots and leave 1/4 in at channel joints.
  • Fascia cover laps facing the street show every joint; start at the far end so each 1 in lap faces away from the approach.
  • Insulation stuffed into the eaves blocks the vents you just installed; baffles go in before the soffit, one per rafter bay.
  • Unscreened gaps where the soffit meets the rake let wasps, birds and squirrels in; IRC R806.1 wants every opening under 1/4 in.
  • A 1x6 on 2x8 rafter tails leaves 1-3/4 in of tail showing; 5-1/2 in tails take 1x6, 7-1/4 in tails take 1x8.

Key facts

  • Vinyl soffit panels are 12 in wide and 12 ft long (12 sq ft); aluminum panels are 16 in x 12 ft (16 sq ft). Both come solid or vented.
  • Fascia boards are 1x6 for 2x6 rafter tails and 1x8 for 2x8 tails; aluminum fascia cover comes in 6 in and 8 in widths in 12 ft lengths to wrap them.
  • F-channel nails to the wall and holds the inner edge of the soffit; J-channel or the fascia lip holds the outer edge.
  • IRC R806.2 requires 1 sq ft of net free vent area per 150 sq ft of attic floor. It drops to 1 per 300 when 40 to 50% of the vents sit at least 3 ft above the eaves.
  • Soffit width equals the horizontal overhang: 12 to 24 in on most houses, and up to 36 in on ranch and prairie styles.

Frequently asked questions

How do I calculate soffit square footage?

Add the eave and rake lengths, multiply by the soffit width in feet, and add 10% waste. 180 ft of run with 16 in soffits is 240 sq ft, or 264 sq ft with waste.

How many soffit panels do I need?

Divide the soffit area with waste by the panel coverage: 12 sq ft for vinyl, 16 for aluminum. 264 sq ft of soffit takes 22 vinyl panels or 17 aluminum panels.

How many of the soffit panels should be vented?

Enough to give half the attic's required vent area at the eaves. A 1,500 sq ft attic with a ridge vent (1/300 rule) needs 360 sq in of intake, about 36 ft of fully vented panel. On a 120 ft eave that is every third panel. Without a ridge vent the 1/150 rule calls for vented panel the whole way.

What is the difference between J-channel and F-channel?

F-channel mounts on the wall and holds the inner edge of soffit panels; J-channel mounts at the fascia for the outer edge. You need one length of each equal to the total run, unless the fascia cover has a built-in lip.

Sources and references

Next steps for this project

  1. Roof Pitch
  2. Roofing
  3. Shingles
  4. Rafter Length
  5. Gutters
  6. Soffit & Fascia
  7. Siding

The usual order for a roofing & siding project. See all roofing & siding calculators.

Embed this calculator

Results are estimates based on standard formulas and typical product specifications. Confirm quantities with your supplier and local code before ordering.